    Process is power. LFG switchboards follow a defined, quality-driven production path that ensures accuracy, speed, and ownership at every handoff.

    Our average lead time is 20 weeks—less than half the industry average. And when schedule demands it, we expedite delivery in just a few weeks.

    Fast-Tracked Production Process

    By controlling sourcing, fabrication, coating, and assembly in-house, LFG removes supply chain friction and compresses production timelines without quality compromise.

    Switchboard-Design

    IN-HOUSE
    SWITCHBOARD DESIGN

    • Switchboard-specialized designers develop products, tailored to the demands of the project and its installation
    • A digital build sheet outlines every component and element in 3D modeling—ensuring accuracy from first bend to final bolt
    LFG-Inventory

    MATERIAL SOURCING
    FROM VAST INVENTORY

    • Direct sourcing of all critical raw materials to maintain full control over availability, quality, and cost
    • Years of stocked breaker and busduct inventory through strategic partnership with Siemens and LS Electric. Off-the-shelf components means fractional lead times
    our-process-tab-2-component-parts-preparation

    COMPONENT & PARTS PREPARATION

    • Piranha 12kW fiber lasers for copper & steel cutting
    • Two Piranha 180-ton hydraulic press brakes for custom bends on steel and copper enclosures, frames, and structural components
    • In-house powder coating bay and oven. Customizable paint colors available
    our-process-tab-3-production-assembly

    PRODUCTION &
    ASSEMBLY

    • UL-certified assembly team with 250+ years combined experience and deep expertise across OEM brands
    • Each section is tagged and identified for clarity in the field
    • Internal alignment and build quality verification before quality testing
    Switchboard-Torque-Testing

    Testing & Quality Control

    • Detailed exterior and interior inspection
    • Connectors are torqued
(per UL 891), marked, and documented for field
    • Components are cross-checked against submittal and digital build documents
    • Thorough in-house testing processes, including Hipot (High Potential) testing
    Switchboard-3D-Field-Verification

    Field Verification

    • Review your equipment in 3D before a single component is assembled—verifying feeders, access points, and layouts
    • Our team conducts a hands-on, pre-installation quality check to ensure seamless field execution
    • Project’s Distribution Superintendent or Foreman visits our manufacturing facility to inspect boards, validate design details, and make any adjustments prior to delivery 
    Switchboard-Shipping

    Shipping Preparation & Transport

    • Boards are carefully wrapped, labeled, crated, and sequenced for efficient field installation
    • LFG transportation fleet and staff delivers every switchboard directly to site with full tracking; no third-party loads or pitstops
    our-process-alt-content-ongoing-support

    Energization & Ongoing Support

    • Professional switchboard energization completed efficiently, on your schedule
    • Expert technicians are available for on-site service within 72 hours

    • Every board backed by 18-month warranty with extended terms available

    • Years of critical components stocked in-house enables fast-turnaround replacements